Question 1 7 ( 4 points ) One project has 4 5 activities, 1 9 of which are on the critical path. The estimated average

Question 17(4 points)
One project has 45 activities, 19 of which are on the critical path. The estimated average time for the critical path is 120 days. The standard deviation along the critical path is 8. Please choose the correct answer by using PERT analysis.
What is the probability that the project can be completed AFTER 125?
0.3085
0.7340
0.4255
0.2660
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Essentials Of Strategic Management

Authors: J. Hunger, Thomas Wheelen

5th Edition

0136006698, 9788120348615

More Books

Students also viewed these General Management questions