Question

1 Approved Answer

Question 1 7 Calculate the expected time using the following information. Optimistic time = 3 days Most Likely time = 5 days Pessimistic time =

Question 17
Calculate the expected time using the following information.
Optimistic time =3 days
Most Likely time =5 days
Pessimistic time =7 days
ET=a+4m+b6
7 days
5 days
8 days
4 days
6 days
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Organization Theory And Public Management

Authors: Jonathan R. Tompkins

1st Edition

053417468X, 978-0534174682

More Books

Students also viewed these General Management questions

Question

=+ (d) Restrict the range of summation in (5.51) to 0x

Answered: 1 week ago