Question

1 Approved Answer

Question 1 A project manager evaluates how the project went and celebrates the team's hard work. What phase of the project life cycle are they

Question 1

A project manager evaluates how the project went and celebrates the team's hard work. What phase of the project life cycle are they implementing?

1 point

Close the project

Execute and complete tasks

Initiate the project

Improve and control

2.

Question 2

As a project manager, you documented the deliverables for a project and showcased the project's value to leadership. The project has been approved. What is the next phase of the project lifecycle?

1 point

Execute the project

Initiate the project

Plan the project

Close the project

3.

Question 3

What is the term for a set of guiding principles and processes for owning a project through its life cycle?

1 point

Waterfall methodology

Life cycle methodology

Project management methodology

Project life cycle

4.

Question 4

As a project manager, you need to plan the catering for the week-long company retreat. The budget is very tight and catering is precise. What is the best project management methodology to use?

1 point

Lean Six Sigma Methodology

Agile methodology

Define methodology

Waterfall methodology

5.

Question 5

As a project manager, you start a project with concrete timelines and strict deliverables. What project management methodology should you use?

1 point

Scrum methodology

Control methodology

Waterfall methodology

Agile methodology

6.

Question 6

What phase in the Lean Six Sigma methodology involves identifying gaps and issues from the data collected through surveys and reports?

1 point

Measure

Impact

Control

Analyze

7.

Question 7

Which of the following are project manager responsibilities during the initiation phase? Select all that apply.

1 point

Create a budget

Define project goals

Get project approval

Determine resources needed

8.

Question 8

Which of the following are project manager responsibilities during the closing phase? Select all that apply.

1 point

Complete the project proposal

Confirm acceptance of the project outcome

Reflect on lessons learned

Ensure all tasks are complete

9.

Question 9

A project manager has identified the major milestones of the project and what tasks make up each milestone. What project phase have they just completed?

1 point

Make a plan

Close the project

Execute the project

Initiate the project

10.

Question 10

Which project management approach is an Agile framework that delivers products through an iterative process?

1 point

Scrum

Lean

Waterfall

Six Sigma

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Rethinking Prestige Branding: Secrets Of The Ueber-Brands

Authors: Wolfgang Schaefer, J P Kuehlwein

1st Edition

0749470038, 9780749470036

More Books

Students also viewed these General Management questions

Question

Relax your shoulders

Answered: 1 week ago

Question

Keep your head straight on your shoulders

Answered: 1 week ago