Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Consider a project with 7 activities as represented in table 1 above. The predecessors of each activity and the duration of the activities are

Consider a project with 7 activities as represented in table 1 above. The predecessors of each activity and Activity Predecessors A B  D E F G A B B C C,D E,F Duration (days) 3 2 5 4 9 2 1 No. of compressors needed 6 

Consider a project with 7 activities as represented in table 1 above. The predecessors of each activity and the duration of the activities are given. The number of compressors (consider it as a resource) required by each activity is also listed. The organization has only 6 compressors available for the project. Table 2 below represents the Gantt chart of the project. Table 1 Activity A C E G D Duration (days) 3 2 5 9 1 4 2 No. of compressors 1 needed 1 5 4 6 2 - s 9 9 10 11 12 13 14 15 16 17 18 19 20 21 22 Using a histogram, level the resources. After resource levelling what is the project duration? Activity Predecessors A B D E F G A B B C C,D E,F Duration (days) 3 2 5 4 9 2 1 No. of compressors needed 6 1 5 2 4 4 6

Step by Step Solution

3.44 Rating (147 Votes )

There are 3 Steps involved in it

Step: 1

The detailed answer for the above question is provided below The project duration is 18 days Resourc... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Introduction To Management Science

Authors: Bernard W. Taylor

13th Edition

0134730666, 978-0134730660

More Books

Students also viewed these General Management questions

Question

=+b) Test an appropriate hypothesis and state your conclusion.

Answered: 1 week ago