An electrical contracting company has been awarded a government contract to install lighting fixtures on a major highway. They want to use a horizontal

 

An electrical contracting company has been awarded a government contract to install lighting fixtures on a major highway. They want to use a horizontal bar chart to plan the schedule for the contract with work to begin on January 1 and assuming four weeks per month. The company has established the following project activities, their precedence relationships, and their estimated durations: Immediate Duration Activity a. order materials Predecessors (weeks) 4 b. clear job sites c. excavate job sites d. make trenches for conduit e. install conduit f. form and pour foundations g. install wire h. install lighting standards j. install luminaries j. connect to service 6. 10 b 6 10 8 f 6. 5 h 4 3 a) Perform the AON network and support your answer with relevant analysis and computation. b) When does activity "d" begin? c) When does activity "f" end? d) When is the optimum duration for this project to be completed? Justify your answer e) Identify the critical activity for the project. f) Identify the critical path. g) Although the PERT or CPM network or analysis is prepared, but you are required to speed up the completion of the project. How do you decide on the activities to complete the project sooner? Justify your answer.

Step by Step Solution

3.37 Rating (169 Votes )

There are 3 Steps involved in it

Step: 1

a A network diagram is a graphical representation of a project using the relationship between each task Here we have given each activity preceding act... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Document Format ( 2 attachments)

PDF file Icon
6363e53fdfe13_236799.pdf

180 KBs PDF File

Word file Icon
6363e53fdfe13_236799.docx

120 KBs Word File

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Business Statistics

Authors: Robert A. Donnelly

2nd Edition

0321925122, 978-0321925121

More Books

Students also viewed these Accounting questions