QUESTION 1 b) c) Month Forecast January 300 February 320 March 320 April 340 May 320 June 320 Regular Output Overtime Output Subcontracting Develop a
QUESTION 1 b) c) Month Forecast January 300 February 320 March 320 April 340 May 320 June 320 Regular Output Overtime Output Subcontracting Develop a Level Output Plan and identify the total short units in each period and overall in production cycle Develop Chase Output Plan(s) to address the shortage identified in the Level Output Plan. Recommend the most cost-effective plan Capacity Units per Month 300 20 Unlimited $ per Unit 40 50 60