Question 1 Developers and Testers are working in a Sprint which has only two days left for Sprint closure. Development for all the stories are
Question
Developers and Testers are working in a Sprint which has only two days left for Sprint closure. Development for all the stories are completed but Testers may not be able to test all the stories before the closure of the Sprint. Since development is completed, what should the developers do at this stage?
Developers should pick up the stories of next Sprint and start working on it so that the stories can be assigned to Testers next Sprint starts
Developers should check the feasibility for collaborating with Testers to complete the testing of the stories before the clo: Sprint
Developers should get clarifications from Product owner on remaining stories and need not involve Testers
Developers must engage in Product Backlog grooming, since the responsibility of testing the stories is with the Testers
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started