Question 1 On January 3rd, Stevens Manufacturing received an order for 25 toasters. Following is the timeline for processing the order: Order processed Wait for
Question 1 On January 3rd, Stevens Manufacturing received an order for 25 toasters. Following is the timeline for processing the order: Order processed Wait for production to begin Raw materials moved to assembly Assembly Wait for packaging Toasters packaged Wait for shipping Toasters loaded and shipped Toasters in transit to customer Days 0.25 2.00 0.25 3.50 0.50 0.25 2.00 0.50 5.00 Calculate the manufacturing cycle efficiency. 33% 50% 100% 2990