Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

QUESTION : 1 outside the critical path. d ) What is the probability of completing the project in 5 3 days? What is the probability

QUESTION : 1 outside the critical path.
d) What is the probability of completing the project in 53 days? What is the probability of completing this project in 48
days?
Question 2
The total budgeted cost (PV) for each of the 15 work packages that make up a project is shown in the table below. The
percentage of work actually completed for each work package, as well as the cumulative PV and actual cost (AC) for each
work package, at a particular review point, are also provided in the table.
a) Compute the schedule variance (SV), cost variance (CV), schedule-performance index (SPI) and cost-
performance index (CPI) for this work package.
b) Compute the 'estimate at completion' using two of the three formulae introduced in the subject. Succinctly state
any conditions (or the rationale) underpinning each of the two formulae used.
c) Identify two practical situations in which each of the above formulae would be preferred?
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management A Managerial Approach

Authors: Jack R. Meredith, Samuel J. Mantel,

7th Edition

470226218, 978-0470226216

More Books

Students also viewed these General Management questions