Question 1 Sheridan Company prepared a fixed budget of 50000 direct labor hours, with estimated overhead costs of $250000 for variable overhead and $90000 for
Question 1 Sheridan Company prepared a fixed budget of 50000 direct labor hours, with estimated overhead costs of $250000 for variable overhead and $90000 for fixed overhead. Sheridan then prepared a flexible budget at 47000 labor hours. How much is total overhead costs at this level of activity? O $319600 O $340000 O $235000 O $325000