Question 1: the following table contains information concerning four jobs that are awaiting processing at a work center. Job Job Time (Days) Due Date (Days)
Question 1: the following table contains information concerning four jobs that are awaiting processing at a work center.
Job | Job Time (Days) | Due Date (Days) | |
A | 15 | 21 | |
B | 7 | 15 | |
C | 10 | 16 | |
D | 6 | 17 | |
a.Sequence the jobs using (1) First come, first served, (2) Shortest processing time, (3) Earliest due date, and (4) Critical ratio. Assume the list is by order of arrival.
b.For each of the methods in parta, determine (1) the average job flow time, (2) the average tardiness, and (3) the average number of jobs at the work center.
c.Is one method superior to the others?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started