The following table represents a schedule of activities for the completion of four new Spanish Hotels in Jamaica:
tableACTIVITYtablePREDECESSOROPTIMISTIC,MOST LIKELY,PESSIMISTICABACADBEBFCDEGFHFIG H
NB: Time periods are in months.
A Draw the activity network for this problem.
B Determine the Expected Time and Variance for each activity.
C Show the activity schedule EST EFT, LST LFT as well as slack. You may work in the network but please show the results in a table.
D Determine and state the critical path for this project. This must be based on your work in c and not by inspection.
E What are the expected time and the variance of the project?
F What is the probability the project will be finished within months?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started