Answered step by step
Verified Expert Solution
Question
1 Approved Answer
Question 1 The information for a project is given in the Table below (time in weeks): Activity Immediate Activity predecessors time (t) A 3 B
Question 1 The information for a project is given in the Table below (time in weeks): Activity Immediate Activity predecessors time (t) A 3 B A 4 B 4 D B 1 E B 1 F B 3 G C, D, E, F 2 H E, F 1 1 G H 2 J 1 1 = a) Draw a network for this project b) Determine the critical path c) Determine the earliest and latest activity times d) Determine slack time for each activity Question 2 The information for a project is given in the Table below (time in weeks): Activity Immediate Activity predecessors time (t) . 8 B A 2 A 3 D 60 E B 60 F 2 G D 2 H EF 20 1 G 10 J H,1 10 J 12 L K 3 a) Draw a network for this project b) Determine the critical path c) Determine the earliest and latest activity times d) Determine slack time for each activity = Question 3 The activities necessary for the completion of one project are listed in the table below. The table reports normal time and normal cost for each activity. Crashed time and cost for each activity are also reported (time in this example is in weeks). Crash the project by 6 weeks with minimum increase in total cost. Each time show the critical path, activity/ies crashed, and total cost of the project. Normal Crashed Time Cost Time Cost Predecesso Activity rs A B D B E B F G D H E F, G, H 4 7 1 4 5 5 2 2 2 30 60 80 40 110 90 60 70 140 T.C = 680 3 5 1 2 2 2 1 1 2 40 200 80 80 275 690 90 110 140 Question 4 The activities necessary for the completion of one project are listed in the table below. The table reports normal time and normal cost for each activity. Crashed time and cost for each activity are also reported (time in this example is in weeks). Crash the project by 4 weeks with minimum increase in total cost. Each time show the critical path, activity/ies crashed, and total cost of the project. Crashed Time Cost Activity Predecesso rs D E F G A B D, E, F Normal Time Cost 3 50 5 60 3 70 10 50 6 100 7 90 5 50 T.C = 470 2 3 2 10 3 4 4 70 180 110 50 250 390 120
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started