Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Question 11 (1 point) When the engineering department needs to assemble a printing machine, so the project team can use it to print a new

Question 11 (1 point)

When the engineering department needs to assemble a printing machine, so the project team can use it to print a new book, this is called a(n)

Question 11 options:

A External dependencies
B Internal dependencies
C Mandatory dependencies
D Discretionary dependencies

Question 12 (1 point)

Two tasks A & B. Task A duration is 6 days and Task B duration is 4 days. If the total time to complete both tasks is 10 days, Task B is dependent on Task A with

Question 12 options:

A A Finish-to-Start dependency
B A Start-to-Start dependency
C A Finish-to-Finish dependency
D None of the above

Question 13 (1 point)

Two tasks A & B. Task A duration is 6 days and Task B duration is 4 days. If Task B is dependent on Task A with a Finish-to-Finish dependency, task A must start

Question 13 options:

A 2 days after Task B Finishes
B 3 days before Task B starts
C At the same time as Task B
D 2 days before Task B starts

Question 14 (1 point)

A project team is tasked with estimating a project cost to build a computer network that connect offices on 4 different continents. The team never done this kind of project before. The best approach to estimate the project cost is to use the following cost estimation method

Question 14 options:

A Parametric Estimate
B Analogous Estimate
C Bottom-up Estimate
D Top-down Estimate

Question 15 (1 point)

Two tasks A & B. Task A duration is 6 days and Task B duration is 4 days. If the total time to complete both tasks is 6 days, Task B is dependent on Task A with

Question 15 options:

A A Finish-to-Start dependency
B A Start-to-Finish dependency
C A Finish-to-Finish dependency
D None of the above

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Fundamentals Of Risk Management

Authors: Clive Thompson, Paul Hopkin

6th Edition

1398602868, 978-1398602861

More Books

Students also viewed these General Management questions