question 11 show all work A line-balancing solution has been developed for the assembly line for fertilizer spreaders at Green Grass, Inc. The desired output
question 11 show all work
A line-balancing solution has been developed for the assembly line for fertilizer spreaders at Green Grass, Inc. The desired output rate of 30 spreaders per hour will be achieved. The sum of times for all tasks performed on the line is 1056 seconds for each spreader assembled. This is the total productive time. Which of the following statements must be TRUE?
Select one:
a. The cycle time is 30 seconds per spreader.
b. If the solution calls for 12 stations, the efficiency is 80%.
c. The theoretical minimum number of stations is 10.
d. If the solution calls for 11 stations, the efficiency is 80%.
on 11
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started