Question 2 1 p t s Which of the following is true about consensus method of estimating project time and costs? Uses ratios to estimate

Question 2
1pts
Which of the following is true about consensus method of estimating project time and costs?
Uses ratios to estimate costs (ex: $? foot)
Utilizes pooled experience of senior managers to estimate duration/cost
Used when there is significant uncertainty associated with the time or cost
Utilizes performance improvement patterns to estimate repetitive work
Allocates a portion of the budget to major elements of work based on historical performance
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Introduction to Risk Management and Insurance

Authors: Mark S. Dorfman, David Cather

10th edition

131394126, 978-0133255409, 133255409, 978-0131394124

More Books

Students also viewed these General Management questions