Question 2 2.1.To cut the number of projects, the steering committee used a weighting scheme that reflected the airline's priorities, which were: fly safe, generate
Question 2
2.1."To cut the number of projects, the steering committee used a weighting scheme that reflected the airline's priorities, which were: fly safe, generate revenue, reduce costs, and customer service. The weighting scheme easily weeded out the fluff." (40 Marks)
Use a weighted scoring model to help the committee choose between two projects: Booking System Upgrade and Cabin Crew Retraining. The relative weights for each criterion and the assessment of each project for these criteria are shown in the following table. Which project would you choose and why? (14 marks)
Criteria | Weight | Booking System Upgrade | Pilot Crew Retraining | |
Fly safe | 40 | 4 | 10 | |
Generate revenue | 30 | 9 | 9 | |
Reduce costs | 20 | 7 | 8 | |
Customer service | 10 | 10 | 10 |
(Assume 10 represents the preferred score and 1 represents the undesired score.)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started