Question 2 3 ( 1 point ) Which of the following does NOT help describe a project network? a Gives the times when activities can
Question point
Which of the following does NOT help describe a project network?
a Gives the times when activities can start and finish and when they can be delayed
b A graphic display of the flow and sequence of work through the project
c Highlights major deliverables and identifies their completion dates
d Provides the basis for scheduling labor and equipment