Question 2 : (30%) Draw the AOA and AON networks for the following project and calculatethe minimum project duration(15%). Activity Duration (days) Immediate Predecessors A
Question 2: (30%)
- Draw the AOA and AON networks for the following project and calculatethe minimum project duration(15%).
Activity | Duration (days) | Immediate Predecessors |
A | 10 | --- |
B | 8 | --- |
C | 2 | A |
D | 4 | A |
E | 5 | B,C, D |
.
- Given the project within the table below calculate the critical path andthe minimum project duration (15%)
Activity | Duration (hours) | Immediate Predecessors |
A | 4 | None |
B | 3 | None |
C | 10 | None |
D | 7 | B,C |
E | 1 | D |
F | 1 | E |
G | 5 | A,F |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started