Question 2 : (30%) Draw the AOA and AON networks for the following project and calculatethe minimum project duration(15%). Activity Duration (days) Immediate Predecessors A

Question 2: (30%)

  1. Draw the AOA and AON networks for the following project and calculatethe minimum project duration(15%).

Activity

Duration (days)

Immediate Predecessors

A

10

---

B

8

---

C

2

A

D

4

A

E

5

B,C, D

.

  1. Given the project within the table below calculate the critical path andthe minimum project duration (15%)

Activity

Duration (hours)

Immediate Predecessors

A

4

None

B

3

None

C

10

None

D

7

B,C

E

1

D

F

1

E

G

5

A,F

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management Process

Authors: Lee Long

4th Edition

978-0201822939,0201822938

More Books

Students also viewed these General Management questions