Question

1 Approved Answer

Question 2 [4 marks]: Use the information provided for the Hinge kit to complete the MRP for the Hinge pin component only. Bill of Materials

image text in transcribedimage text in transcribed

Question 2 [4 marks]: Use the information provided for the "Hinge kit" to complete the MRP for the "Hinge pin" component only. Bill of Materials - Hinge Kit Hinge pin LH hinge plate Level 0 1.1 1.2 1.3 2.0 Description Hinge kit RH hinge plate LH hinge plate Hinge pin Hinge screw Quantity 1 2 2 2 12 RH hinge plate Hinge screws Each kit contains 2 hinges and 12 screws Master Production Schedule - Hinge kit Period 0 1 2 3 4 6 7 8 9 10 Customer demand 1,800 2,200 1,200 1,500 1,900 2,000 1,600 1,400 1,800 2,000 MPS quantity 1,000 2,000 1,500 1,500 1,500 2,000 2,000 1,000 2,000 2,000 Projected on-hand inventory 1,100 300 100 400 400 0 0 400 0 200 200 MPS start 1,000 2,000 1,500 1,500 1,500 2,000 2,000 1,000 2,000 2,000 Component Ordering Policy Component RH hinge plate LH hinge plate Hinge pin Hinge screw Order release multiples 1,000 1,000 2,000 10,000 Minimum on-hand inventory 10,000 10,000 10,000 60,000 Maximum on-hand inventory 15,000 15,000 15,000 90,000 Notes: 1. You do not have to level production 2. Maintain as little on-hand inventory as the ordering policy will allow 2. Maintain min/max inventory levels even in the final period Material Requirement Plan - Hinge pin Period 0 1 2 3 4 5 6 7 8 9 10 Gross requirements Planned receipts Projected on-hand inventory Planned order releases Question 2 [4 marks]: Use the information provided for the "Hinge kit" to complete the MRP for the "Hinge pin" component only. Bill of Materials - Hinge Kit Hinge pin LH hinge plate Level 0 1.1 1.2 1.3 2.0 Description Hinge kit RH hinge plate LH hinge plate Hinge pin Hinge screw Quantity 1 2 2 2 12 RH hinge plate Hinge screws Each kit contains 2 hinges and 12 screws Master Production Schedule - Hinge kit Period 0 1 2 3 4 6 7 8 9 10 Customer demand 1,800 2,200 1,200 1,500 1,900 2,000 1,600 1,400 1,800 2,000 MPS quantity 1,000 2,000 1,500 1,500 1,500 2,000 2,000 1,000 2,000 2,000 Projected on-hand inventory 1,100 300 100 400 400 0 0 400 0 200 200 MPS start 1,000 2,000 1,500 1,500 1,500 2,000 2,000 1,000 2,000 2,000 Component Ordering Policy Component RH hinge plate LH hinge plate Hinge pin Hinge screw Order release multiples 1,000 1,000 2,000 10,000 Minimum on-hand inventory 10,000 10,000 10,000 60,000 Maximum on-hand inventory 15,000 15,000 15,000 90,000 Notes: 1. You do not have to level production 2. Maintain as little on-hand inventory as the ordering policy will allow 2. Maintain min/max inventory levels even in the final period Material Requirement Plan - Hinge pin Period 0 1 2 3 4 5 6 7 8 9 10 Gross requirements Planned receipts Projected on-hand inventory Planned order releases

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Corporate Financial Reporting In A Competitive Economy (RLE Accounting)

Authors: Herman W. Bevis

1st Edition

1138966819, 9781138966819

More Books

Students also viewed these Accounting questions

Question

Give eye contact, but do not stare.

Answered: 1 week ago