Answered step by step
Verified Expert Solution
Question
1 Approved Answer
Question 2: Answer all five questions above, for the following activities. Activity Duration Predecessors 1 week 2 weeks 2 weeks 2.1 Draw the network diagram
Question 2: Answer all five questions above, for the following activities. Activity Duration Predecessors 1 week 2 weeks 2 weeks 2.1 Draw the network diagram along with activity name, early start (ES), early finish (EF), late start (LS), late finish (LF), and duration. 2.2 Write the critical path based on your analysis using the network diagram above (e.g. A- C-F-1). 2.3 What is the total project duration? 2.4 What happens to other tasks if B takes six weeks to complete? Is there any impact on the project duration? 2.5 How much longer duration C can take without any impact on the total project duration
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started