Question 2 options: Remember Do Not format your answers . No $ signs or commas A manager must decide which type of machine to buy,

Question 2 options:

Remember Do Not format your answers . No $ signs or commas A manager must decide which type of machine to buy, either A, B or C. Machine costs are as follows: Machine A $50000 B $70000 C $40000 Each machine will be used to produce 4 different Products. The forecasted demand and processing times on the machines are as follows:

Processing Time Per Unit (Minutes)

Product

Annual Demand

Using Machine A

Using Machine B

Using Machine C

1

24000

4

4

4

2

16000

6

4

6

3

9000

2

1

5

4

3000

4

4

Machines operate 10 hours per day, 250 days per year. Compute the yearly processing time (in minutes) required for each of the different machines. Machine A Processing Time = 222000 Machine B Processing Time = Machine C Processing Time = Assume that only purchasing costs are being considered. The machine with the lowest total cost = (either A, B, or C)

How many of that machine would be needed?

The machines differ in terms of hourly operating costs. Machine A, B, and C have hourly operating costs of $10, $15, and $13 respectively. Annual Operating Cost for Machine A = Annual Operating Cost for Machine B = Annual Operating Cost for Machine C =

Assume that each of the machines has a useful life of 4 years and the annual demand will remain at the same level for each of the 4 years. Total Cost would be the initial cost of the machine(s) plus 4 years of operating costs. Total Cost for Machine A =248000 Total Cost for Machine B = Total Cost for Machine C = The machine Alternative with the lowest total cost (initial cost plus 4 years of operating costs) =

(either A, B, or C)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management A Systems Approach to Planning Scheduling and Controlling

Authors: Harold Kerzner

10th Edition

978-047027870, 978-0-470-5038, 470278706, 978-0470278703

More Books

Students also viewed these General Management questions

Question

8. According to Baumol-Tobin theory demand for money, Mt 2 = bY 2i

Answered: 1 week ago