Question 2: Project crashing (20 marks) Suppose that you are working on a new software product development project. Table below provides the information about the
Question 2: Project crashing (20 marks)
Suppose that you are working on a new software product development project. Table below provides the information about the activities, immediate predecessors, normal times and costs, and crash times and costs.
Activity | Immediate Predecessor(s) | Normal Time (weeks) | Crash Time (weeks) | Normal Cost ($)
| Crash Cost ($) |
A | None | 5 | 2 | 25 000 | 34 000 |
B | None | 4 | 2 | 30 000 | 40 000 |
C | A,B | 10 | 6 | 45 000 | 81 000 |
D | B | 5 | 3 | 30 000 | 38 000 |
E | C,D | 7 | 6 | 30 000 | 37 000 |
F | C | 5 | 3 | 20 000 | 26 000 |
G | E, F | 6 | 4 | 35 000 | 65 000 |
Draw an Activity-on-Arrow(AOA) network diagram to represent the above project. Using normal durations calculate the minimum project completion time and identify the critical path(s).
(5 marks)
Suppose that management wants to shorten the project to 20 weeks to beat competition. Which activities should be crashed, and for each crashed activity provide the total number of weeks crashed and the total crash cost. Illustrate your solution using a crashing table.
(8 marks)
What is the total project crashing cost?
(2 marks)
Draw a Gantt chart for the crashed project, incorporating all task durations, dependencies, free float and the critical path(s).
(5 marks)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started