Question 20 1 pts An assembly line has five workstations. Tasks at Workstation #4 take the longest amount of time to complete with a
Question 20 1 pts An assembly line has five workstations. Tasks at Workstation #4 take the longest amount of time to complete with a total processing time of 65 seconds. 65 seconds is also the required cycle time. The total amount of task time across all workstations is 288 seconds. What is the efficiency of this assembly line? 68.4% 60.6% 92.6% 96.0% 88.6% 76.8% 82.8%