Question 23 (2.5 points) Which one of the following techniques on project risk analysis would usually consider the project outcomes in a worst case, a

image text in transcribed
Question 23 (2.5 points) Which one of the following techniques on project risk analysis would usually consider the project outcomes in a worst case, a base case, and a best case? A) The simulation analysis B) The scenario analysis OC) The risk-return tradeoff analysis D) The sensitivity analysis