Answered step by step
Verified Expert Solution
Question
1 Approved Answer
Question 3 (20 Points) Consider the following project. (5 points each part) Activity Immediate Predecessors ABCDEFG A B, C, D A C, D Duration
Question 3 (20 Points) Consider the following project. (5 points each part) Activity Immediate Predecessors ABCDEFG A B, C, D A C, D Duration 244224 1 Write on the answer sheet a). The slack time of each activity. Which activities are critical? b) What is the total project duration? c) Identify ALL critical paths. How many are there? d) If you would have a chance to reduce the duration of two activities by one time unit each, which two activities would you choose? Will you be able to reduce this way the total project time?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started