The marketing department at Bodnar Industries is developing a promotional campaign to introduce a new product. A listing of the various activities required, their immediate
The marketing department at Bodnar Industries is developing a promotional campaign to introduce a new product. A listing of the various activities required, their immediate predecessors, and estimates of their times (in days) is given below.
a) Draw the precedence diagram for this network.
b) Identify the critical path and the expected project completion time.
For any calculations that you make that involve time, use the time (days) to two decimal places (xx.xx).
Activity | Description | Immediate Predecessors | Optimistic Time | Most Likely Time | Pessimistic Time |
A | Rough brochure layout | -- | 2 | 3 | 5 |
B | Review brochure | A | 6 | 8 | 10 |
C | Final brochure layout | B | 4 | 6 | 8 |
D | Final brochure artwork | C | 5 | 7 | 11 |
E | Design display | -- | 12 | 15 | 20 |
F | Rough display artwork | E | 2 | 3 | 4 |
G | Review display | E | 6 | 8 | 10 |
H | Revise display | G | 2 | 3 | 4 |
I | Final display artwork | F,H | 1 | 2 | 4 |
J | Make display plates | I | 18 | 23 | 26 |
K | Make brochure plates | D,I | 10 | 13 | 16 |
L | Make and ship displays | J | 7 | 10 | 14 |
M | Print and ship brochures | K | 6 | 8 | 10 |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started