Question 3 (30 marks) TCB Limited is a local manufacturer producing subassemblies. MRP planning schedule for one of its Subassembly V is shown as below.

Question 3 (30 marks)

TCB Limited is a local manufacturer producing subassemblies. MRP planning schedule for one of its Subassembly V is shown as below. The ordering lead time is one week.

Subassembly V

Week 0

Week 1

Week 2

Week 3

Week 4

Week 5

Gross requirement

75

50

70

On-hand

40

Net requirement

Planned-order receipt

Planned-order release

Derive the net requirements, planned-order receipts, and planned-order releases to meet the gross requirements. (10 marks)

Discuss whether safety stock shall be included into MRP system by illustrating with real-life example (20 marks)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Essentials of Management

Authors: Andrew J. DuBrin

9th Edition

538478233, 2900538478235, 978-0538478236

More Books

Students also viewed these General Management questions