Question 3 (30 marks) TCB Limited is a local manufacturer producing subassemblies. MRP planning schedule for one of its Subassembly V is shown as below.
Question 3 (30 marks)
TCB Limited is a local manufacturer producing subassemblies. MRP planning schedule for one of its Subassembly V is shown as below. The ordering lead time is one week.
Subassembly V | Week 0 | Week 1 | Week 2 | Week 3 | Week 4 | Week 5 |
Gross requirement | 75 | 50 | 70 | |||
On-hand | 40 | |||||
Net requirement | ||||||
Planned-order receipt | ||||||
Planned-order release |
Derive the net requirements, planned-order receipts, and planned-order releases to meet the gross requirements. (10 marks)
Discuss whether safety stock shall be included into MRP system by illustrating with real-life example (20 marks)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started