Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Question 3: LCC For this problem, you will need to refer to the class notes as well as the supplemental readings under Life Cycle Costing

Question 3: LCC For this problem, you will need to refer to the class notes as well as the supplemental readings under Life Cycle Costing

Assume the construction start date is January 2019. You are a manager choosing between two designs for new capital facilities. Given the facts below, calculate the LCC for each alternative and make a recommendation.

For each alternative:

The time horizon is 30yrs. Real interest rate is 3% Nominal interest rate is 7% Assume the cash flows are EOY cash flows and happen once per year starting at year 1. Each alternative has a construction duration of 2 years. The construction starts at January 2019. Construction costs incurs as equivalent uniform annual cost over the construction duration. The building location is in Texas. There is no salvage value for each alternative design. *Note. Salvage value is NOT residual value check notes The bank is providing a loan at 8% compounded annually for the construction costs. o There are no payments on the loan during the construction period. o You must pay pack the loan in 15 equal installments starting at year 3. The loan finance rate will be 8%.

Alternative One Construction cost is $4 million USD, including Energy usage is natural gas and electrical: o Projected annual natural gas use is $16,500 o Projected annual electricity use is $7,000 The mechanical system has the following parameters: o Lifespan is 35 years starting at the service date (The first use is incurred at year 3, because it has been in service for 1 year.) o Initial cost is $350,000 (which is included in the $4 million construcimage text in transcribed

Question 3: LCC For this problem, you will need to refer to the class notes as well as the supplemental readings under Life Cycle Costing Assume the construction start date is January 2019. You are a manager choosing between two designs for new capital facilities. Given the facts below, calculate the LCC for each alternative and make a recommendation. For each alternative The time horizon is 30yrs. Real interest rate is 3% Nominal interest rate is 7% Assume the cash flows are EOY cash flows and happen once per year starting at year l * Each alternative has a construction duration of 2 years. The construction starts at January 2019 . Construction costs incurs as equivalent uniform annual cost over the construction duration. . The building location is in Texas " There is no salvage value for each alternative design. *Note. Salvage value is NOT residual value check notes The bank is providing a loan at 8% compounded annually for the construction costs. . o There are no payments on the loan during the construction period. o You must pay pack the loan in 15 equal installments starting at year 3. The loan finance rate will be 8%. Alternative One Construction cost is $4 million USD, including *Energy usage is natural gas and electrical o Projected annual natural gas use is $16,500 o Projected annual electricity use is $7,000 The mechanical system has the following parameters Lifespan is 35 years starting at the service date (The first use is incurred at year 3, because it has been in service for 1 year.) Initial cost is $350,000 (which is included in the $4 million construction cost) o o Operations and maintenance are S125,000 per year (not including energy) Question 3: LCC For this problem, you will need to refer to the class notes as well as the supplemental readings under Life Cycle Costing Assume the construction start date is January 2019. You are a manager choosing between two designs for new capital facilities. Given the facts below, calculate the LCC for each alternative and make a recommendation. For each alternative The time horizon is 30yrs. Real interest rate is 3% Nominal interest rate is 7% Assume the cash flows are EOY cash flows and happen once per year starting at year l * Each alternative has a construction duration of 2 years. The construction starts at January 2019 . Construction costs incurs as equivalent uniform annual cost over the construction duration. . The building location is in Texas " There is no salvage value for each alternative design. *Note. Salvage value is NOT residual value check notes The bank is providing a loan at 8% compounded annually for the construction costs. . o There are no payments on the loan during the construction period. o You must pay pack the loan in 15 equal installments starting at year 3. The loan finance rate will be 8%. Alternative One Construction cost is $4 million USD, including *Energy usage is natural gas and electrical o Projected annual natural gas use is $16,500 o Projected annual electricity use is $7,000 The mechanical system has the following parameters Lifespan is 35 years starting at the service date (The first use is incurred at year 3, because it has been in service for 1 year.) Initial cost is $350,000 (which is included in the $4 million construction cost) o o Operations and maintenance are S125,000 per year (not including energy)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Principles Of Financial Accounting Ch 1 17

Authors: Robert Libby, Patricia Libby, Fred Phillips, Stacey Whitecotton

1st Edition

0077370457, 9780077370459

More Books

Students also viewed these Accounting questions

Question

How would you describe Mark Zuckerberg as a team leader?

Answered: 1 week ago