Question 3 On March 1, 2015, Lancelot Company entered into a contract to build an apartment building. It is estimated that the building will cost
Question 3
On March 1, 2015, Lancelot Company entered into a contract to build an apartment building. It is estimated that the building will cost $2,200,000 and will take 3 years to complete. The contract price was $2,700,000. The following information pertains to the construction period:
2015
2016
2017
Annual Costs
$800,000
$1,100,000
$700,000
Estimated costs to complete
1,400,000
1,100,000
0
Yearly Progress billings
700,000
1,000,000
1,000,000
Yearly Cash collected
880,000
1,100,000
720,000
Required:(Round percentages toexcludedecimal points and round dollar amounts toexcludecents)
Assuming thepercentage-of-completionrevenue recognition method is used.
- Compute the amount of revenue and gross profit to be recognized each year
- Prepare the all necessary journal entries for each year.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started