Question 3: Percentage of Completion Method (12 marks) On January 1, 2017, Eagle Construction Ltd. started a construction project for $4,500,000. Relevant data for 2017

Question 3:

Percentage of Completion Method (12 marks) On January 1, 2017, Eagle Construction Ltd. started a construction project for $4,500,000. Relevant data for 2017 and 2018 are as follows:

2017 2018

Current year construction costs $3,300,000 $ 620,000

Estimated remaining costs to complete 600,000 -0-

Current year billings 3,100,000 1,400,000

Current year collections 3,000,000 1,500,000

Required: Calculate the following amounts for each method:

Completed Percentage-of Contract Completion 2017 2018 2017 2018

a) Gross Profit $ $ $ $

b) Construction in progress year-end balance $ $ $ $

c) Costs in excess of billings (Billings in excess of costs) $ $ $ $

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Accounting What the Numbers Mean

Authors: David H. Marshall, Wayne W. McManus, Daniel F. Viele,

9th Edition

978-0-07-76261, 0-07-762611-7, 9780078025297, 978-0073527062

Students also viewed these Accounting questions