Question
Question 3: Percentage of Completion Method (12 marks) On January 1, 2017, Eagle Construction Ltd. started a construction project for $4,500,000. Relevant data for 2017
Question 3:
Percentage of Completion Method (12 marks) On January 1, 2017, Eagle Construction Ltd. started a construction project for $4,500,000. Relevant data for 2017 and 2018 are as follows:
2017 2018
Current year construction costs $3,300,000 $ 620,000
Estimated remaining costs to complete 600,000 -0-
Current year billings 3,100,000 1,400,000
Current year collections 3,000,000 1,500,000
Required: Calculate the following amounts for each method:
Completed Percentage-of Contract Completion 2017 2018 2017 2018
a) Gross Profit $ $ $ $
b) Construction in progress year-end balance $ $ $ $
c) Costs in excess of billings (Billings in excess of costs) $ $ $ $
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started