Question
1 Approved Answer
Question 3 The following information summarizes the company's cost structure: Variable cost per unit $1.50 Fixed cost per unit 4.5 Total cost per unit $5.80
Question 3 | |||||||||
The following information summarizes the company's cost structure: | |||||||||
Variable cost per unit | $1.50 | ||||||||
Fixed cost per unit | 4.5 | ||||||||
Total cost per unit | $5.80 | ||||||||
Units produced and sold | 45,000 | ||||||||
Assume that all of the activity levels mentioned in this problem are within the relevant range. | |||||||||
Required: | |||||||||
how would you prepare a schedule showing predictions for the following items at the 40,000-unit level of activity. Round answers to two decimal places. | |||||||||
a. Total variable cost. (1 Mark) | |||||||||
b. Total fixed cost. (1 Mark) | |||||||||
c. Variable cost per unit. (1 Mark) | |||||||||
d. Fixed cost per unit.(1 Mark) | |||||||||
Note: The total fixed cost is $4.50 45,000 = $202,500. |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started