Question 38 (1 point) A customer wants to contract 15 units of a product with a learning rate of 0.9. The first unit took 30
Question 38 (1 point) A customer wants to contract 15 units of a product with a learning rate of 0.9. The first unit took 30 hours to produce. What is the average time to produce the 15 units the customer wants? Answer to 2 decimal places and without units.
QUESTION 39 You have a process that includes three components. The first component has a reliability of 0.89, the second has a reliability of 0.89, and the third has a reliability of 0.87. What is the reliability of the system? Answer to three decimal places.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started