Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Question 4 (30 marks) a. As the Project Manager for the EduStream project, it is now time to prepare an update for the weekly planning

image text in transcribed
Question 4 (30 marks) a. As the Project Manager for the EduStream project, it is now time to prepare an update for the weekly planning meeting (Week 8), which is due in about an hour. Unfortunately, your Microsoft Project is off-line, so you will have to conduct the Earned Value Management (EVM) analysis for this part of the project manually. Use the information here to assess the current situation and then answer the questions on the following page. (15 Marks) Activity Predecessor Duration Cost $ Budget Activity (Weeks) (Per Cost (BC) In the cells below, use dark blue to indicate the Precedence Diagramming Method schedule and red to illustrate the percent completed. Week) A $5,500 $11,000 3 $6,400 $19,200 A 2 $7,600 $15,200 D B 5 $6,000 $30,000 E B, C 10 $9,500 $95,000 F C 5 $5,200 $26,000 G B 10 $3,800 $38,000 BAC $234,400 Week 1 2 3 4 5 6 7 8 9 10 12 13 14 15 Progress Report Today (end of Week 8 - Complete this table Cost Implications Schedule Implications Shown by the thick red line) Activity % Complete Incurred Activity AC EV PV CPI CV SPI SV Cost (ACWP) (BCWP) (BCWS) 100% $12,100 A 100% $18,500 B 50% $16, 120 C The CPI, CV, SP! and SV are not required for the 40% $12,750 individual Activities. Only calculate these values for the 70% $51,300 E totals. 40% $18,000 30% 59,700 Total

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management A Systems Approach to Planning Scheduling and Controlling

Authors: Harold Kerzner

10th Edition

978-047027870, 978-0-470-5038, 470278706, 978-0470278703

More Books

Students also viewed these General Management questions

Question

Examine various types of executive compensation plans.

Answered: 1 week ago

Question

1. What is the meaning and definition of banks ?

Answered: 1 week ago

Question

2. What is the meaning and definition of Banking?

Answered: 1 week ago

Question

3.What are the Importance / Role of Bank in Business?

Answered: 1 week ago