Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Question. 4: In the given table and network diagram below, a small engineering project activities durations and direct costs under both normal and crash conditions

image text in transcribed
image text in transcribed
Question. 4: In the given table and network diagram below, a small engineering project activities durations and direct costs under both normal and crash conditions are provided. Normal Crash Cost Preceded Activity Duration Cost Duration by Cost Slope (day) (SR) (day) (SR) (SR/day) A 7 3600 3900 300 B 5 5500 3 6500 500 C 9 7 7200 ? D B 19 4700 18 4900 200 E B 10 2050 9 2200 150 F 8 1200 7 1450 250 G 1 5 7200 5 7200 ? H 11 9450 10 10000 550 1 D. GH 2 4500 5 4600 SO 6350 It is required to crash the project duration from its original duration to a final duration of 38days. Assume an indirect cost of SR 200/day. Use Project information to perform all needed cycles and use them to answer the following questions What is the cost slope for activity C What is the cost slope for activity OT Question Completion Statue It is required to crash the project duration from its original duration to a final duration of 38days. Assume an indirect cost of SR 200/day. Use Project information to perform all needed cycles and use them to answer the following questions: What is the cost slope for activity C? What is the cost slope for activity G? In order to reduce the project duration which activity/activities would be crashed in cyclewi? In order to reduce the project duration which activity/activities would be crashed in cycle 2? In order to reduce the project duration further (ie less than 38 days) which activity activities would be crashed next? by how many days the project can be shortened in cycel 1 by how many days the project can be shortened in cyoel22 by how many days the project can be shortened in Cycel 3 At what duration the total cost direct cost indirect cost) is the smallest optimal duration Question. 4: In the given table and network diagram below, a small engineering project activities durations and direct costs under both normal and crash conditions are provided. Normal Crash Cost Preceded Activity Duration Cost Duration by Cost Slope (day) (SR) (day) (SR) (SR/day) A 7 3600 3900 300 B 5 5500 3 6500 500 C 9 7 7200 ? D B 19 4700 18 4900 200 E B 10 2050 9 2200 150 F 8 1200 7 1450 250 G 1 5 7200 5 7200 ? H 11 9450 10 10000 550 1 D. GH 2 4500 5 4600 SO 6350 It is required to crash the project duration from its original duration to a final duration of 38days. Assume an indirect cost of SR 200/day. Use Project information to perform all needed cycles and use them to answer the following questions What is the cost slope for activity C What is the cost slope for activity OT Question Completion Statue It is required to crash the project duration from its original duration to a final duration of 38days. Assume an indirect cost of SR 200/day. Use Project information to perform all needed cycles and use them to answer the following questions: What is the cost slope for activity C? What is the cost slope for activity G? In order to reduce the project duration which activity/activities would be crashed in cyclewi? In order to reduce the project duration which activity/activities would be crashed in cycle 2? In order to reduce the project duration further (ie less than 38 days) which activity activities would be crashed next? by how many days the project can be shortened in cycel 1 by how many days the project can be shortened in cyoel22 by how many days the project can be shortened in Cycel 3 At what duration the total cost direct cost indirect cost) is the smallest optimal duration

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Accounting questions

Question

5. How would you describe your typical day at work?

Answered: 1 week ago

Question

7. What qualities do you see as necessary for your line of work?

Answered: 1 week ago