Question
Question 4 Nova Companys total overhead cost at various levels of activity are presented below: Month Machine- Hours Total Overhead Cost April 70,000 $ 198,000
Question 4
Nova Companys total overhead cost at various levels of activity are presented below:
Month Machine- Hours Total Overhead Cost April 70,000 $ 198,000 May 60,000 $ 174,000 June 80,000 $ 222,000 July 90,000 $ 246,000
Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 60,000 machine-hour level of activity is:
Utilities (variable) $ 48,000 Supervisory salaries (fixed) 21,000 Maintenance (mixed) 105,000 Total overhead cost $ 174,000
Nova Companys management wants to break down the maintenance cost into its variable and fixed cost elements.
Required:
1. Estimate how much of the $246,000 of overhead cost in July was maintenance cost. (Hint: to do this, it may be helpful to first determine how much of the $246,000 consisted of utilities and supervisory salaries. Think about the behavior of variable and fixed costs.)
2. Using the high-low method, estimate a cost formula for maintenance in the form Y = a + bX.
3. Express the companys total overhead cost in the form Y = a + bX.
4. What total overhead cost would you expect to be incurred at an activity level of 75,000 machine-hours?
4 Month April May June July Machine- Hours 70,000 60,000 80,000 90,000 Total Overhead Cost $ 198,000 $ 174,000 $ 222,000 $ 246,000 2.5 points Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 60,000 machine-hour level of activity is: eBook Print Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) Total overhead cost $ 48,000 21,000 105,000 $174,000 References Nova Company's management wants to break down the maintenance cost into its variable and fixed cost elements. Required: 1. Estimate how much of the $246,000 of overhead cost in July was maintenance cost. (Hint: to do this, it may be helpful to first determine how much of the $246,000 consisted of utilities and supervisory salaries. Think about the behavior of variable and fixed costs.) 2. Using the high-low method, estimate a cost formula for maintenance in the form Y = a + bx. 3. Express the company's total overhead cost in the form Y = a + bx. 4. What total overhead cost would you expect to be incurred at an activity level of 75,000 machine-hoursStep by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started