Question 4 You are providing a status for a 14-week project, which is scheduled to be 50
Question:
Question 4
You are providing a status for a 14-week project, which is scheduled to be 50 percent complete at this time. You have completed 9 of the 16 deliverables in this project and spent $1200 of the total project cost of $1900.
What is the Earned Value (EV)?
Round your answer to 2 decimal places. Question 7
You are providing a status for a 14-week project, which is scheduled to be 50 percent complete at this time. You have completed 9 of the 16 deliverables in this project and spent $1200 of the total project cost of $1900.
What is the Schedule Performance Index (SPI)?
Round your asnwer to 2 decimal places. l: Question 8
You are providing a status for a 14-week project, which is scheduled to be 50 percent complete at this time. You have completed 9 of the 16 deliverables in this project and spent $1200 of the total project cost of $1900.
What is the Cost Performance Index (CPI)?