Question 4 : You are the project manager for a smart watch development project. The project has a budget of SAR 1 5 0 ,

Question 4:
You are the project manager for a smart watch development project. The project has a
budget of SAR 150,000 to develop the smart watch with advanced health monitoring
features, fitness tracking, and seamless smartphone integration. The project timeline is
9 months for a total of 1,400 hours. According to the project schedule your team
should be done with 65% of the work which is planned to cost 35% of the budget.
As of today, the project is 45% complete while 25% of the budget has been used.
From the given information, determine the following and then answer the question
below.
Answers:
BAC=
PV=
AC=
EV=
CV=
SV=
CPI =
SPI =
EAC=
ETC=
How is the project doing? ) there any problems? Why?
Is it ahead of schedule or behind schedule and Why?
Is it under budget or over budget and Why?
Based on the performance to the date, what the project will cost to complete?
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Thinking In Circles About Obesity Applying Systems Thinking To Weight Management

Authors: Tarek K. A. Hamid

2009th Edition

0387094687, 9780387094687

More Books

Students also viewed these General Management questions

Question

Prove that P(A'B') = 1 + P(AB) P(A) P(B).

Answered: 1 week ago