Question #48 of 180 While acquiring resources, what would be the LEAST likely reason to update the project team assignments? O A) A team
Question #48 of 180 While acquiring resources, what would be the LEAST likely reason to update the project team assignments? O A) A team member was promoted to another position within the organization and will no longer be on the team. B) A team member was diagnosed with a serious medical condition and must be on medical leave for an indefinite period of time. O C) A team member retired from your company with 30 years of service. O D) A team member moved to another country.