Question
QUESTION 5 (20 Marks) The following performance report summarizes budget and actual usage and costs for the items shown for a particular month in which
QUESTION 5 (20 Marks)
The following performance report summarizes budget and actual usage and costs for the items shown for a particular month in which 100 SeaCruiser hulls were produced by Cruiser Inc.
Raw materials: Budget Actual Variance Glass fiber clotT 45 780 46125 345 U Budget Standard/hull of 218 meters @$2.10/m x 100 hulls Actual: 22 500 m @2.05/m
Direct labour: Budget Actual Variance Build up labour: 33280 32 893 387 F Budget Standard/hull of 26 hrs @$12.80/hr x 100 hulls Actual: 2 540/hrs @12.95/hr
Variable overhead: Budget Actual Variance
8320 8128 192 F Related to build up labour Budget: Standard/hull of 26hrs @$3.20/hr x 100 hulls Actual: 2 540hrs @ $3.20/Hr
Total 87 380 87146 234 F
Required
Analyse the budget variance for each item by calculating the quantity and cost per unit of input variances.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance