Question 5 (8 marks) The following project has three independent paths as shown in the project network diagram. The deadline to complete this project
Question 5 (8 marks) The following project has three independent paths as shown in the project network diagram. The deadline to complete this project is 46 days. Most B Optimistic Pessimistic Expected Variance Likely Activity Time Time Time of Time (days) (days) (days) Activity (days) Start A 10 16 28 11 D End B 20 28 42 C 18 30 42 E 1 1 F D 15 15 15 E 1 2 3 F 42 45 45 48 a) What is the probability that this project will be delayed?