QUESTION 5 After 1 0 months, a project's budgeted ( or planned ) cost is $ 2 4 0 0 . The actual cost is
QUESTION
After months, a project's budgeted or planned cost is $ The actual cost is $ and the earned value is $ What is the schedule variance SV of the
project at this time? Enter a positive or negative number without the dollar sign. For example, if the answer is $ enter
Step by Step Solution
There are 3 Steps involved in it
Step: 1