Question 5. Having calculated the WACC in the previous question, use that number to calculate the answer There are three different projects that have been

Question 5.

Having calculated the WACC in the previous question, use that number to calculate the answer There are three different projects that have been sent to you in the finance department. These projects have been deemed mutually exclusive, so after research you must decide which project that you should recommend to senior management.

Year Project A Project B Project C

0 (1,200) (8,000) (4,000)

1 725 3,500 1,000

2 350 2,000 800

3 200 2,000 1,700

4 100 2,000 1,700

5 500 2.500 1,700

WACC = 10%

What are the NPV and IRR for projects A, B, and C?

Project A: NPV: IRR:

Project B: NPV: IRR:

Project C: NPV: IRR:

Which project would you recommend and why?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Finance questions