Question 6 (11 points) Flynn Construction Company signed a contract on June 15, 2019 to construct an office building. The contract price for the building

image text in transcribed
Question 6 (11 points) Flynn Construction Company signed a contract on June 15, 2019 to construct an office building. The contract price for the building is $6,500,000. Construction started in June 2019 and was completed in late 2020. The company has a December 31 year end. Information for the contract is as follows: 2019 2020 Costs incurred during the year $2,400,000 $3,000,000 Estimated costs to complete as of December 31 2,600,000 Billings during the year 2,950,000 3,550,000 Collections during the year 2,500,000 3,700,000 Assume that Flynn uses the percentage-of-completion method of accounting for long term contracts. Required: Prepare the journal entries to record the transactions in 2020 assuming that Flynn Construction follows IFRS. Space is provided below for calculations and a general journal is provided for journal entries. Dates are not required for journal entries. Format V B I U Calculations

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Internationale Rechnungslegung IFRS Praxis

Authors: Author

1st Edition

3834909289, 9783834909282

More Books

Students also viewed these Accounting questions

Question

What is the mass of 25.0 cm3 of iron?

Answered: 1 week ago

Question

How to Calculate the Regression Line

Answered: 1 week ago

Question

Understand the use of different performance-rating techniques

Answered: 1 week ago