Question 6 (15 points) Calculate CPI and SPI for the following project at the end of day 6. Activity Predecessor Duration Cost/ Day (days)
Question 6 (15 points) Calculate CPI and SPI for the following project at the end of day 6. Activity Predecessor Duration Cost/ Day (days) Actual % Complete at end of day 6 Actual Cost at end of day 6 A 2 300 100 600 B A 4 400 96 1850 C B 3 250 12 165 D B 2 300 0 0