Question
1 Approved Answer
Question 7 (1 point) 9) A project manager is considering how to structure a project team that will not directly disrupt ongoing operations. The
Question 7 (1 point) 9) A project manager is considering how to structure a project team that will not directly disrupt ongoing operations. The project needs to be done quickly and a high level of motivation will be needed in order to do that. For this situation, the organization would be the best choice. A) functional OB) balanced matrix C) weak matrix OD) strong matrix E) projectized