Question 7 1 Point If interest rate is 11%, find the NPV of this project and decide if you should accept or reject it. Year
Question 7 1 Point If interest rate is 11%, find the NPV of this project and decide if you should accept or reject it. Year O: CF = -400 Year 1: CF = 100 Year 2: CF = 500 Year 3: CF = -200 A NPV = 149.21 So Reject BNPV = 434.54 so Accept CNPV = -34.54 so Accept D NPV = -50.34 so Reject