Question
1 Approved Answer
Question 7 5 pts If three activities are using the same resource, the network diagram must be draw to show the three activities performed at
Question
pts
If three activities are using the same resource, the network diagram must be draw
to show the three activities performed at the same time.
to show the three activities so that none is a predecessor of the others.
to show a serial relationship for the activities.
to show the activity sequence with technical constraints only