Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Consider the following table and Progress Report to answer the questions given below: Activity Predecessor Time(days) Estimated Cost A None IS 90 B None

 

Consider the following table and Progress Report to answer the questions given below: Activity Predecessor Time(days) Estimated Cost A None IS 90 B None 2 $120 A S 200 ID IC 1 IS 60 E C $100 Progress Report The project started on Sunday and we received the following progress report at the end of Tuesday (day 3): Activity A is Completed 100%, and the cost incurred is 80S Activity B is Completed 100%, and the cost incurred is $100 Activity C is completed 90% and the cost incurred is $150 a. Draw a Gantt chart for the above-mentioned activities and reflect the progress report values on it. b. Calculate PV, EV and AC for the above-mentioned activities by considering the progress report. c. Calculate the following variances and interpret the results: i. Schedule Variance (SV) ii. Cost Variance (CV) d. Calculate the following indexes to monitor performance and interpret the results i. Schedule Performance Index (SPI) ii. Cost Performance Index CPI e. Calculate the Estimated total Cost at completion (EAC) f. Draw cost/schedule graph showing PV, EV, AC, SV, CV, EAC and BAC based on the above-mentioned calculations.

Step by Step Solution

3.38 Rating (151 Votes )

There are 3 Steps involved in it

Step: 1

a b Planned ValuePV Planned value is the approved value of the work to be completed in a given timeT... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Economics Today

Authors: Roger LeRoy Miller

16th edition

132554615, 978-0132554619

More Books

Students also viewed these Computer Network questions

Question

How is the economic production quantity different from EOQ?

Answered: 1 week ago