Question 7 ( Mandatory ) Assuming you are doing both Backlog Refinement and Sprint Planning in the same session, order the activities below: 4 Estimate
Question Mandatory
Assuming you are doing both Backlog Refinement and Sprint Planning in the same session, order the
activities below:
Estimate the story using planning poker
Pick the next highest priority story from the Product Backlog
Refine the story by working with the product owner.
Develop a set of Acceptance Criteria for the story
Add the story to the sprint backlog if it "fits"
Ensure the Story has the Proper Definition of Done
Draft a possible implementation along with tasks
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started